Table 1: Main Summary (table-labor cost.html) ✓ Multi-level headers detected with <th> tags
No. Item Name Item Features Unit Statistics of Completion Data Current Period Data Cumulative Data Remarks
Budget Revenue Planned Cost Budget Revenue Actual Cost Budget Revenue Actual Cost
Quantity Unit Price Total Price Quantity Unit Price Total Quantity Unit Price Total Price Quantity Unit Price Total Price Quantity Unit Price Total Price Quantity Unit Price Total Price
I Basement Structure 2347723.93 2769234.86 -45348.83 -64500 2297592.47 2434226.18
II Podium Structure 446612.47 440819.86 0 0 365302.72 342138.71
III Tower 1 Structure 1541884.54 1453947.23 176749.46 173500.82 679877.49 643023.32
IV Tower 2 Structure 1487934.54 1985433.89 114448.34 110419.82 630370.18 591426.06
V Basement Decoration 349846.63 437613.82 54164.86 57457.52 199010.79 235821.72
VI Podium Decoration 107776.35 148939.80 43205.08 58739.92 107227.63 122181.10
VII Tower 1 Decoration 115598.76 146861.40 0 0 0 0
VIII Tower 2 Decoration 155019.01 210637.60 0 0 0 0
Total 6552396.23 7593488.46 343218.91 335618.08 4279381.27 4368817.09
Table 2: Main Structure (table-labor cost_3.html) ✓ Separate sub-table
Item Amount
Main Structure Rebar & Concrete 4010814.27
Main Structure Formwork & Scaffolding 6636335.91
Tower Crane Signaling & Operation 255600
Main Structure Civilized Construction 756575
Total Main Structure Cost 11659325.18
Cumulative Actual Reported Quantity 12623760.37
Table 3: Secondary Structure (table-labor cost_4.html) ✓ Separate sub-table
Item Amount
Secondary Structure Masonry 358002.82
Secondary Structure Decoration 1093058.66
Total Secondary Structure Cost 1451061.48
Cumulative Actual Reported Quantity 2298298.15